LAST STAND

 
 
 

Visit us on Facebook

 
 

Home

About Us

Hot Topics

Calendar

Donations  

Join Us!

What's New?

Our Stands

Green Links

Last Stand Blog

As much noise as was made about how carefully carried out the Key West Harbor dredging project would be, the coral damage caused by the Navy's dredging contractor is inexcusable.  Editorial from the April 26 Key West Citizen:

Harbor dredging is necessary, surprises about damage are not

A $36 million project by the Navy to make the main shipping channel into Key West Harbor 34 feet deep to allow for large military vessels was first criticized by some residents who said the Navy wasn't providing enough details about the dredging. The Navy responded with public meetings.

Then local turtle advocate Richie Moretti of the Marathon Turtle Hospital screamed that the so-called hopper dredger — to be used for the first month of the 18-month effort — would grind up turtles along with the sand, rock and debris it was supposed to smash to bits. The Navy responded that it had taken appropriate precautions, had explored Moretti's suggestions and found them inadequate.

In the past two weeks, The Citizen has learned that the Navy's contractor, Bean-Stuyvesant, hit coral March 22 as its crew guided the hopper dredger through waters off Key West, and that it's possible there's more damage.

We're hoping for an appropriate response from the Navy, and its contractor, this time, too.

Bean-Stuyvesant reported the March 22 coral damage to Navy officials, who in turn alerted the Army Corps of Engineers, the federal agency that granted the dredging permit.

This was the appropriate action to take, and it would be nice if the damage reported is the only case of the massive dredger banging into a precious resource for both sea life and humans.

The Florida Keys National Marine Sanctuary and state wildlife officials are investigating several areas that might have been hit, but wouldn't talk about the possible locations last week or how many of them are being checked out. The sanctuary also is assessing the loss from the March 22 incident.

Meanwhile, the Navy's contractor is consulting with the Army Corps of Engineers, the Florida Keys National Marine Sanctuary, which regulates waters off the Keys, and the Navy to figure out how to avoid further coral damage.

Since these types of meetings also are said to have taken place prior to the start of dredging, we wonder why these conversations didn't take place then.

Surely the experts planning for the massive dredging operation could have predicted some bumping around that might bring equipment dangerously close to patches of coral.

In fact, there were some efforts to preserve coral in the channel before the dredging began, as some was transplanted to other places in preparation for the project.

The dredging is a major undertaking, supported even by Florida Keys National Marine Sanctuary officials who say the silt that sits at the bottom of the channel gets stirred up by cruise ships as they pass through the harbor and smothers coral. A deeper channel should help, they say.

Is the tradeoff of digging a deeper harbor to allow for cruise ships and large military ships to pass through — with the added benefit of eliminating silt buildup on patches of coral — worth the damage caused in the process?

It has to be. The military needs access to the harbor, and in this era of doing all that is necessary to secure our homeland, there was never a question about whether the project would be done.

But the coral damage seems to have caught those involved in the process off-guard, and the public, too. That is surprising, considering the experts knew the scope of this project and the type of equipment being used.

Now we all know the possibility of coral being damaged during the next year and a half.

We urge local marine experts, sanctuary officials and representatives of the Army Corps of Engineers to put together a realistic strategy for minimizing future damage.

 RETURN TO HOT TOPICS

RETURN TO HOME PAGE